Monday, May 31, 2010

Skylight and Bulkhead

Despite threatening rain, we got the skylight in on Saturday. Brian came up to help and the job was pretty well finished before lunch time. Tiles were cut and put in place and when the rain came later in the afternoon there were no drips on the floor.
 
I think Brian is having a "lightbulb" moment here after reading the instructions.
This sash is very heavy. The instructions show a very relaxed clean-cut young tradesman putting this in on his own. I don't think so!!

I have spent more time sanding and plastering the Gyprock joints in the pantry and we might get some paint on the walls next weekend.

The major visual change this week has been the Gyprock on the main bulkhead. This was a fairly easy job. It's so much easier dealing with small sheets.
The first bit going in under the bulkhead.

And the last bit for this weekend.

Monday, May 24, 2010

More Gyprock

We have had a very productive weekend. After deciding against using the very cheap ($100) Velux sky window for the kitchen due to space constraints we went for a Skydome similar to our existing skylight. With the hole in the roof and the skydome sitting in place it became obvious that the Velux had to come back into the plan as there was just not enough light. This meant cutting out two rafters and then boxing in to fit the sky window. A much longer process so it isn't finished yet. Enough was done to work out where the main Gyprock sheeting was going so on Sunday with Mark and Tony's help we got most of the new ceiling sheeted.

Prior to putting up the Gyprock it was necessary to put battens alongside each rafter to "true up" the ceiling line. Otherwise we would have had a very wavy ceiling.


With the scaffold propped over the stairs again we got the two sheets up in the highest part of the ceiling.



 

Looking good so far. Then it was on to the main ceiling, fitting insulation batts as we went.



 

Tony managed to turn insulation installation into performance art.


And that was the finish for the weekend. The blue sarking is where the sky window will be next weekend if the weather holds.

Tuesday, May 4, 2010

A Month Later

Progress has been slow of late with a few extraneous issues getting in the way and fiddly details to work out but at last Gyprock is going up.
 
Glenn and James have spent a fair time here and have created a maze of wiring but it is a very neat maze. 
The new "fuse"box in the pantry with a couple of wires. This is so much neater than the old box stuck on the wall, partly because this one is actually recessed into the wall and with its doors shut it looks great.
 Even in these conditions the 25th of April couldn't pass without a few biscuits.
When this sheet went up we started to see the shape of the finished product, something we had had to imagine up to this point. The new air conditioner will end up on this bulkhead.
Setting up the scaffold over the stairs was a delicate balancing act but was very secure when tied to the side wall. Probably not OH&S standard but it did the job well and much better than standing on a ladder and lifting a sheet of Gyprock. Trouble is, now that the wall on the left has been lined, there is nowhere to sit our supporting plank. We'll think of something.
Tony finally makes an appearance. Not his best side though. 
Some things are just too tricky for Ellie & I to do on our own.
Starting to look very neat. Those black rafters will be covered in soon and all will be white.
Note "Blog Central" through the door at the bottom of the stairs.
Another shot of the main kitchen. The space for the leadlight windows has been left over the beam in the foreground.

Monday, April 5, 2010

A few studs

It was finally time to put up the last beam to complete the bulkhead. With the beam up I was able to start filling in above the beams with studs, ready for the Gyprock after Glenn has finished his roughing in.





Having completed a run of studs.....


.... it was time for a good red. I needed a third hand for the cheese and crackers but you can't always get what you want (as someone once said). Next step was to fill in the back of the fridge/freezer alcove. To save precious centimetres we opted for a plywood wall rather than conventional studs and Gyprock. Ellie sanded and painted the sheets...

...and then I put them up.

 It doesn't look much but it was good to see this coming together. The plywood wall always had a small question mark over it but once it was in place I knew it was OK.
The second of the pantry shelves was taken out next to allow for removal of more old Gyprock.


The pantry shelves can just be seen in the background, standing in the hallway. It's a bit like coming into a supermarket now when you come in the front door.

Friday, March 26, 2010

A bit of Gyprock

Another door has to go, not far, but it will be turned around.
 
With the door out of the way I could lift some more of the old vinyl tiles. Brian's compressor and mini "jack hammer" were invaluable with this.
                                
After this we had assistance from Tony to get a couple of sheets of Gyprock up in the pantry while we could still get the scaffolding in there.
 
Ellie and I would have had a lot of trouble doing this on our own but because we were all otherwise engaged with the ceiling, Tony missed out on a photo. Now it looks like I did it all by myself. Pretty good eh ?
Ellie having breakfast in the mess. Surely, not all messes are this messy ?
View from above the alcove which will hold the fridge and freezer. Looking out through the laundry to the back door.
 Unfortunately we had another surprise when removing the corner of the laundry wall. This pipe turned out not to be under the concrete in this area as expected. $280 later it was out of the way.
And that's it for another weekend.

Thursday, March 18, 2010

More beams

Serious things are happening now. This beam, which was an afterthought put in when the front wall of the pantry was constructed, is now going.
Before it could go, the pantry wall had to go, which meant removing Ellie's lead-light windows. These were taken down and packed away carefully, awaiting a new wall to support them.

It wasn't long before the windows were out and the cladding coming off. Ellie got into the swing of it as the lower boards became accessible. 
Time to put up the first beam on the pantry side so Ellie was up on the scaffold like a shot.
 
The beam is up but what is it for ? It seems to be floating. This is building in reverse. First put up your beam, then support it with something !
 
Forget the support. Let's put up another one.
 
So there is the result (with a rather naked pantry) although that beam will continue next week. We also finished the beams on the window side too.

Thursday, March 4, 2010

It continues

The spaces under the windows have been bricked up on the inside and the boxes for power points and switches have been set in to the wall. Ellie is using her new "island" bench for cooking, frothy coffee in hand to make light of the work.
 

The next step was to complete the removal of the wall at the end of the hallway. This included replacing the supporting post which holds the central beams (the ones which don't line up). I was quite nervous doing this because although everything was propped up temporarily, a lot of weight seemed to be on one stud which should not have been holding up anything. Anyway, it all turned out OK.

 

This isn't the offending post. That was the one which the white one on the left replaced.



With all the timber out of the way I was able to finish the bagging at the corner of the hallway. That strip doesn't look like it's been done but the difference is that we have refined our method with the bagging as we have gone along and now we can leave a fairly clean surface. The concern now is that it might show through the paint.